This project included the installation of a new sanitary sewer line, removal and replacement of existing sanitary sewer line, spot repair of existing sanitary sewer, installation of new storm drains, installation and traffic control for new box culvert and 120” RCP. Elite Surface Infrastructure also installed new concrete curb and gutter, sidewalk, aprons and drive lanes. ESI repaired existing site concrete. ESI realigned and built drop structures on an existing gulch that is heavily contaminated with ACM (Asbestos Containing Material). Although the entire site contains ACM, the gulch required a 401 and 404 permits that are closely monitored by the state of Colorado to insure that no asbestos enters a waterway. In order to build the box structure, the 120” RCP and the gulch requires an extensive water diversion plan and erosion control plan in conjunction with the 401 and 404 permits.